When it’s better for a subcontractor to walk away from a federal deal

Victor K • June 15, 2023
A construction worker wearing a hard hat and safety vest is making a funny face.

Things go south when subcontractors are not included in government and contractor negotiations. In the recent past, the US Air Force decided to redo a small construction project. However, the main contractor signed the contract without the consultation of the subcontractor. The actual cost increased, and a dispute was filed with the Armed Services Board of Contract Appeals. Tom Temin spoke with Boone Haynes procurement attorney Dan Ramish for more details on the fiasco.

 

Tom: I think it started when the Air Force changed the ground rules when they decided to do additional work in the form of an alarm system.

 

Dan: I agree. Optimum Construction, a contractor, was awarded a $2 million project to replace a fire alarm system at Eglin Air Force Base. The Air Force changed the contract, shifting the work hours and sequence, which increased costs for Optimum and its subcontractor, Pugh. Optimum initially negotiated with Pugh and the Air Force to capture the changes but faced pressure from the Air Force to agree to a $200,000 modification or risk contract termination. Optimum accepted the modification without consulting Pugh, leading to significantly reduced costs for the subcontractor. The case ended up before the Armed Services Board of Contract Appeals.

 

Tom: Right, Optimum Construction wanted $100, 000 whereas the Air Force agreed to 200, 000 and the subcontractor ended up getting $13,000 instead of the original ask of $100 000.

 

Dan: Yes, Optimum Construction failed to consult with its subcontractor, Pugh, before agreeing to a $200,000 modification. The subcontractor later discovered that the modification did not account for all their costs, as the work was scheduled for nights and required demobilization and remobilization daily, impacting their expenses.

 

Tom: yes, but Optimum paid whatever extra it could to Pugh. What happened next when Pugh wasn't happy with the new deal?

 

Dan: After completing the work, Pugh submitted a Request for Equitable Adjustment (REA) to Optimum Construction for additional costs of $90,000, similar to their original proposal. Optimum, however, expressed surprise and skepticism about the subcontractor's claim. As expected, the Air Force rejected the REA, and when Optimum converted it to a claim, the contracting officer also denied it.

 

Tom: It wasn't over, and an additional dispute was claimed. What did the Armed Services Board of Contract Appeals decide?

 

Dan: The board concluded that there was no additional constructive change as the subcontractor's concerns were already addressed in a previous modification. They emphasized that Pugh proceeded with the work despite raising the issue with the main contractor. The modification included release language, indicating a settlement for the changes. Optimum's claim of signing the modification under duress was dismissed since the government had the right to terminate the contract for convenience.

 

Tom: Right, the dispute now becomes between the main and subcontractor because the government got the job done at the price they wanted.

 

Dan: That’s correct. Main contractors face the challenge of avoiding being caught in the middle when dealing with modifications that affect subcontractors. The main contractor must involve the subcontractor in negotiations to align their interests and secure approval. Failing to obtain subcontractor approval and making disparaging comments can lead to dissatisfaction and potential legal action by the subcontractor against the main.

 

Tom: So in such situations, the subcontractor should just walk away from the table?

 

Dan: Well, if the subcontractor had been involved in the decision-making process and given a choice between a lower $200,000 modification or walking away, they might have made a similar decision. However, since they were not engaged during the modification, the main contractor may now be caught in the middle and incur costs that cannot be recovered from the government.

 

Tom: So what would be your advice to the main contractor if they were your client?

 

Dan: When dealing with a bilateral modification, it is essential to carefully review and understand its coverage. It may be challenging or even impossible to seek additional compensation for the same work due to the inclusion of a standard release. Therefore, addressing subcontractor costs and schedule upfront is advisable, significantly when the subcontractor raises concerns about inadequate coverage.

 

Tom: so, no assumptions about the modified terms and additional payments?

 

Dan: Absolutely correct. The board concluded that the main contractor said it would take about 800 to 900 thousand dollars to get the work done, which eventually was done in $300,000. The gap in this costing and work cost was the basis of the decision against the subcontractor. Therefore, it is better to know the terms and walk away when you can.

 

Therefore, consultation with an expert is essential before taking up big projects. This rule is religiously followed by United Seattle, so there are next to zero disputes, and suppliers or further subcontractors are not dealt a bad hand.

By Victor K • September 22, 2026
General contractors or GC often look out for a complete package in their commercial subcontractor Seattle. The enormous task of combining multiple commercial construction subcontractor Seattle for a single project is a recipe for disaster and all GCs know this well. However, when it comes to selecting that one, the cost bid must not be the only criterion. The lowest bid might not have the overall expertise that is required for the project. GCs can bundle all the tasks and award them to one construction management subcontractor. However, the cost comparison between a single commercial subcontractor Seattle or multiple ones is not linear as lower coordination costs, fewer scope gaps, and better schedule control must also be taken into account. Total Installed Cost Vs. Trade Pricing In simple mathematical terms, the total project cost is just the amount the commercial subcontractor Seattle charges the GC. However, factors like Trade bid price, coordination cost, schedule exposure and change-order exposure must also be taken into account while pricing for a singular or multiple construction management subcontractors. The GC can simply request a quote for each task, generate competition and get the lower cost. However, the factors listed account for additional cost in this scenario as the GC needs to coordinate multiple contracts, schedules, site mobilizations, foremen, RFIs, submittals, invoices, inspections, and handoffs. A single-source commercial subcontractor Seattle like United Seattle may cost more than a competitive breakdown of subtasks but the additional factors are eliminated and long-term cost and time savings are achieved. Schedule Float Vs. Small Bid Difference Multiple tasks have multiple timelines which are often linear rather than parallel. This means that one commercial construction subcontractor Seattle needs to wait for the other one to complete their task before starting. An ideal example of this is flooring and drywall installation. One cannot be done before the first task is completed. A delay in the earlier task can lead to delays, extra cost and rising disputes, all of which have a price tag that the GC has to pay. Therefore, calculations are to be carried out before using multiple contractors rather than one. For example, if a bundled subcontractor costs $30,000 more than the combined lowest trade bids but gives the project team additional schedule flexibility and reduces the likelihood of a costly sequencing delay, that $30,000 should not be evaluated in isolation.
By Victor K • September 14, 2026
Learn how to vet a commercial subcontractor before signing. Check licensing, bonding, insurance, safety, capacity, references, and project management.
By Victor K • August 25, 2026
Managing a construction project is not just about outsourcing all the tasks; it involves much more than meets the eye. It is about being on the project from start to end and checking that all timelines are being followed by every commercial subcontractor Seattle. Scheduling and adhering to timelines are among the most challenging tasks, as it can result in loss of time and resources. The ideal method for a general contractor is to select a commercial construction subcontractor Seattle that provides all the required services. The result can be a more coordinated workflow, clearer accountability, and fewer opportunities for one trade to disrupt another.= The Challenge of Managing Multiple Trade Subcontractors Generally, a major construction job consists of multiple facets, resulting in the hiring of multiple commercial subcontractors in Seattle. These tasks include siding , roofing, flooring , interior design and paint jobs . Different construction management subcontractors bring different flavors to the table and managing them takes special skills on the part of the general contractor. These various companies also bring their own timelines which can result in slowing down the project as most of these tasks need to be completed in a series manner rather than in parallel. The main challenge is not the number of commercial subcontractor Seattle involved in the project but handling their cohesiveness. Every additional handoff creates another opportunity for something to fall through the cracks.
More Posts

We Offer All the Services You Need in One Place! We Will Save You Time and Money!

Call Us at (425) 332-8088 Now to Get a Free Estimate or a Free Consultation for Any of Our Services!

Contact Us